Block C&D now coming to completion with the final works being completed to the hoist infill and corner details, Mast strikes now commencing to block C with D to follow.
Block A continuing to progress with our cavity works now at level 16 and brick work facade following behind at level 8-12.
Block B and E mast Installation now in progress, more updates to follow.