Scaffold Strike Commencing on Outwood Wharf…

25 September 2024

Scaffold strike commencing on Outwood Wharf…

– Elevation 5 is at level 4.5
– Elevation 7 and 8 at level 7
– Elevation 9 is at 6.5
– Elevations 10 and 6 are now fully down

Fitters are now completing cavity works on the final floor to the crown level 22. Progress has been made in hoist flats we are now at level 17 leaving 5 floors to go.

Amazing Work!!🧱👏🏻
Jordan Bray

 

MORE ARTICLES

Learning from Experience…

Good to see apprentices eager to learn!

More Good News to Start the Week…

Another project win to start in 2025!

Circle Square Update….

We are proud of the progress our Circle Square site is making!

Project Win….

Project win starting 2025!

Progress at Waterhouse Gardens…

Great progress being made at Waterhouse Gardens!

Completed Castings Project…

Happy to unveil photographs taken from the recently completed Castings project!

I-PAF Demonstrator Training…

New Training Completed- I-PAF Demonstrator

Project Update…

Project Update…

Apprentice Appreciation…

Apprentice Appreciation…

Collaboration and Communication are Key…

Collaboration and Communication are Key…