Preparation is so important on a job that is 60% soffits and support. Pillar and detail work with the brick will be made easy if we keep to the plan.
A) get all of the ground floor blockwork complete (one less task to worry about)
B) point all soffits on the ground inside the building and store safely
C) fix angle support and soffits with great precision
A tricky detail job like this is only so if it’s not planned, fixers to get 3-5 floors complete at least then brickwork can commence on the scaffold. Watch this space.
Block C&D now coming to completion with the final works being completed to the hoist infill and corner details, Mast strikes now commencing to block C with D to follow.
Points Cross – United Living – Leeds
Preparation is so important on a job that is 60% soffits and support. Pillar and detail work with the brick will be made easy if we keep to the plan.
A) get all of the ground floor blockwork complete (one less task to worry about)
B) point all soffits on the ground inside the building and store safely
C) fix angle support and soffits with great precision
A tricky detail job like this is only so if it’s not planned, fixers to get 3-5 floors complete at least then brickwork can commence on the scaffold. Watch this space.
Well done team