Outwood Wharf – Making Good Progress Over The Last Couple Of Weeks
24 April 2024
Outwood Wharf – Making good progress over the last couple of weeks with the cavity works and masonry support now up to level 19 in advance of our brick layers, we are currently progressing the brick work through level 15 and level 21 ππ»πͺπ»π§±
650,000 brick to lay, 2,500 meters of angle support, 11,000 m2 of cavity work, 8,000 meters of fire barriers – all in 50 weeks; made possible with collaboration from both the main contractor and other familiar sub contractors.
QA – With the introduction of the golden thread of information within the new building safety act (BSA) it is now more important than ever to document our work on site.
A huge well done to our trainee assistant site manager Ellis Jones for winning the Ani Card Health and Safety Award from our client BCEGI UK for his time on Church Street site ππ»